December Update: The arena in the final phase

We are now approaching one of the most exciting milestones in the club's history. Work on the new arena is entering its final stages.

go back

Clubhouse and hall almost finished

The inner part of the arena is now very close to completion. Almost all the walls are painted, and the hall has really begun to gain its final expression. Next week, the final team will be added to the indoor tennis courts — a big step on the road to a complete, player-ready arena.

Outdoor work goes according to plan

The outdoor area is also beginning to take shape. The road up to the arena is almost finished and the parking area is now in its final stages. At the same time, we are working on a clear and safe entrance for pedestrians and cyclists. Terraces and grandstands have been fully laid. Everything is still on track to be completed according to plan. The only thing that will have to wait until spring is planting.

Rebranding — a new chapter for the club

Our rebranding went exactly as planned and we are incredibly excited to adopt the new brand fully in everything we do. This includes both visual profile, communication and the new arena experience. The next step is to fine-tune the website, add more content and make sure everything is clear, modern and easy to use.
The biggest highlight, of course, will be the new club brand. When the order opens, you will receive an email directly — so stay tuned!

Soon we will open memberships in Court22

While the construction work runs its course, we are working in parallel to make everyday life easier for our members. Over the coming week we plan to open up membership to Court22 so you can explore all the features the new system offers. This will be a huge technological boost for the club.
You will soon receive more information in your inbox, including a step-by-step guide on how to complete your membership.